School & District News » November 2026 bond update: Three Springs Elementary steel framing begins, new workforce housing townhomes approved

November 2026 bond update: Three Springs Elementary steel framing begins, new workforce housing townhomes approved

Funded by the 2024 Investing in Our Schools bond, these milestone projects ensure modern facilities and critical support for DSD educators and students.

Citizens' Bond Oversight Committee (CBOC)

The committee continues to meet monthly with the purpose of overseeing the process, validating that spending conforms to ballot language, and reviewing the budget.

Long-Range Planning Committee (LRPC)

The LRPC reconvened in late October to continue researching and proposing plans for future school replacements. This work includes considering school consolidations and a full district boundary analysis after the DSD Board of Education adopted the committee's recommended triggers on the topic. The committee will meet every two months, with some exceptions around upcoming holidays.

Three Springs Elementary School (TSES)

Work on the Wilson Gulch roadway and the school site continues to progress. Although recent regional flooding cost the construction team some days, the project is in its early stages, and DSD does not anticipate a significant schedule impact while the team evaluates how to make up the time. Most foundations have been poured, and structural steel framing is set to begin in the coming weeks. Recently, the third-grade classes from Florida Mesa Elementary School and Sunnyside Elementary School — the first graduating class from Three Springs Elementary School — took a field trip to the construction site.

Workforce Housing

DSD's housing program is currently at approximately 94% occupancy. Since the October update, the Board has approved the purchase of three additional townhomes currently under development off Florida Road, bringing the total number of townhomes being purchased for the program to nine. Adding these nine homes in summer 2027 will bring geographic and unit-type diversity to the district's workforce-housing portfolio, a priority identified during recent focus groups.

Master Schedule

A copy of the master schedule will be included in all future updates. It is critical to note that with a program this large, things may change along the way. 

Fall 2025

  • Fleet replacements at Transportation (partially completed; will be ongoing through bond)
  • Technology replacements (partially completed; ongoing through bond)
  • Durango Big Picture High School renovations begin (completed)

Spring 2026

  • Low-flow water fixture scope (completed)

Summer 2026

  • Deferred maintenance scope at Needham Elementary School, Riverview Elementary School, Animas Valley Elementary School, and Florida Mesa Elementary School (completed)
  • Asphalt/concrete scope, districtwide (completed)
  • Roofing scope at Needham Elementary School and Riverview Elementary School (completed)
  • Furniture replacements — Phase 1 (completed)
  • Media center carpet replacement at Needham Elementary School, Animas Valley Elementary School, and Escalante Middle School (completed)
  • Facilities warehouse renovations (completed)
  • Wilson Gulch Drive improvements, related to Three Springs Elementary School (work ongoing; nearing completion)

Summer 2027

  • Deferred maintenance scope at Durango High School — Phase 1, Escalante Middle School, and Transportation (scoping process has begun)
  • The Hub renovations (scoping process has begun)
  • Furniture replacements — Phase 2 (scoping process has begun)

Summer 2028

  • Deferred maintenance scope at Durango High School — Phase 2, Park Elementary School, Sunnyside Elementary School, and Fort Lewis Mesa Elementary School
  • Escalante Middle School renovations/improvements scope
  • Florida Mesa Elementary School repurpose scope (TBD)
  • Furniture replacements — Phase 3 (TBD)